Your consulting firm has recently been hired to complete a site survey for a company desiring an indoor coverage WI-AN. Your engineers use predictive design software for the task, but the company insists on a pre-design site visit.
What task should be performed as part of the pre-design visit to prepare for a predictive design?
A.
Install at least one AP on each side of the exterior walls to test for co-channel interference through these walls
B.
Collect information about the company's security requirements and the current configuration of their RADIUS and user database servers
C.
Test several antenna types connected to the intended APS for use in the eventual deployment
D.
Evaluate the building materials at the facility and confirm that the floor plan documents are consistent with the actual building