You are using a site survey tool for post-implementation validation. You have installed the appropriate adapter driver and imported a floor plan. Now, you want to take the next step in proper tool use. What must you do before gathering survey data after the floor plan is imported?

A.
Calibrate the floor plan
Answers
A.
Calibrate the floor plan
B.
Install WinPCAP
Answers
B.
Install WinPCAP
C.
Nothing, you can simply start capturing signal readings
Answers
C.
Nothing, you can simply start capturing signal readings
D.
Install iPerf
Answers
D.
Install iPerf
Suggested answer: A

Explanation:

Calibrating the floor plan is what you must do before gathering survey data after the floor plan is imported when using a site survey tool for post-implementation validation. A site survey tool is a software application that can run on a laptop, tablet, smartphone, or other device that has a Wi-Fi adapter and a GPS receiver. A site survey tool can scan the wireless environment and collect information about the detected access points and client stations, such as their SSID, BSSID, channel, signal strength, security, and data rate. A site survey tool can also measure and display various metrics of network performance, such as throughput, jitter, packet loss, delay, and SNR. A site survey tool can also use a floor plan to visualize the wireless coverage and quality in different locations on a map. A floor plan is an image file that shows the layout and dimensions of a building or an area where the WLAN is deployed. A floor plan can be imported from various sources, such as a CAD file, a PDF file, an image file, or a Google Maps screenshot. After importing a floor plan into a site survey tool, it is necessary to calibrate the floor plan before gathering survey data. Calibrating the floor plan means adjusting the scale and orientation of the floor plan to match the actual size and direction of the area. Calibrating the floor plan can be done by using a reference point or a reference line that has a known distance or angle in the real world.Calibrating the floor plan ensures that the survey data is accurate and consistent with the physical environment.Reference:1, Chapter 7, page 290;2, Section 4.3