Question 48 - D-ISM-FN-23 discussion
A Fibre Channel switch has eight ports and all ports must be operational from 6 AM to 6 PM, Monday through Friday.
However, a failure of Port 4 occurs with the week as follows:
Monday= 11 AM to 1 PM
Wednesday= 5 PM to 10 PM
Thursday= 7 AM to 10 AM
Saturday= 11 AM to 1 PM
What is the availability of Port 4 in that week?
A.
80%
B.
86.7%
C.
90%
D.
81 6%