A Fibre Channel switch has eight ports and all ports must be operational from 8 AM to 8 PM, Monday through Friday. However, a failure of Port 2 occurs on a particular week as follows:

Monday = 10 AM to 12 PM Wednesday = 4 PM to 9 PM Thursday = 4 PM to 7 PM

Friday = 3 PM to 6 PM Saturday = 9 AM to 1 PM

What is the availability of Port 2 in that week?

A.
70%
Answers
A.
70%
B.
71.6%
Answers
B.
71.6%
C.
78.3%
Answers
C.
78.3%
D.
80%
Answers
D.
80%
Suggested answer: B