While on-site installing a Dell EMC PowerStore T system, the node A embedded module management Ethernet port link LED is off. What does this indicate?

A.
Port speed is 10 GB/s
Answers
A.
Port speed is 10 GB/s
B.
Network connection is established
Answers
B.
Network connection is established
C.
Port speed is 1 GB/S
Answers
C.
Port speed is 1 GB/S
D.
No network connection is established
Answers
D.
No network connection is established
Suggested answer: D

Explanation:

When the link LED of the node A embedded module management Ethernet port is off, it indicates that there is no network connection established. The link LED is typically used to indicate the presence of a network connection and its status. If the LED is off, it means that the Ethernet port is not currently connected to a network or there is an issue preventing the connection from being established1.

In the case of the Dell EMC PowerStore T system, the embedded module management Ethernet ports are used for network management traffic. It is essential that these ports have an active network connection for the system to be managed remotely. If the link LED is off, the following steps should be taken:

Check the physical connection of the Ethernet cable to ensure it is securely plugged into both the node's port and the corresponding switch or router port.

Verify that the switch or router is powered on and functioning correctly.

Ensure that the correct port on the switch or router is being used and that it is configured correctly for the PowerStore system.

If the issue persists after checking the physical connections and switch/router configuration, consult the Dell EMC PowerStore T Installation and Service Manual for further troubleshooting steps2.

It is important to resolve any network connection issues promptly to maintain the manageability and accessibility of the PowerStore system. Following the official Dell documentation and support resources will help ensure that the system is installed and configured correctly for optimal performance and reliability.