Which command is used to initiate a Storage Controller power supply replacement for XtremlO cluster ABC123?

A.
replace-storage-controller-prepare cluster-id='ABC123'
Answers
A.
replace-storage-controller-prepare cluster-id='ABC123'
B.
replace-storage-controller-psu sc-psu-id=1 cluster-id='ABC123'
Answers
B.
replace-storage-controller-psu sc-psu-id=1 cluster-id='ABC123'
C.
replace-storage-controller-psu cluster-id='ABC123'
Answers
C.
replace-storage-controller-psu cluster-id='ABC123'
D.
replace-storage-controller-prepare sc-psu-id=1 cluster-id='ABC123'
Answers
D.
replace-storage-controller-prepare sc-psu-id=1 cluster-id='ABC123'
Suggested answer: B

Explanation:

To replace a power supply unit (PSU) in a storage controller of an XtremIO cluster, a specific command needs to be executed.

The correct command to initiate this process is replace-storage-controller-psu sc-psu-id=1 cluster-id='ABC123'.

This command specifies the action to replace the PSU (replace-storage-controller-psu), the PSU ID (sc-psu-id=1), and the specific cluster ID (cluster-id='ABC123').

Using this command ensures that the correct PSU in the specified cluster is prepared for replacement.