Katie Holmes has been working as a cloud security engineer over the past 7 years in an MNC. Since the outbreak of the COVID-19 pandemic, the cloud service provider could not provide cloud services efficiently to her organization. Therefore, Katie suggested to the management that they should design and build their own data center. Katie's requisition was approved, and after 8 months, Katie's team successfully designed and built an on-premises data center. The data center meets all organizational requirements; however, the capacity components are not redundant. If a component is removed, the data center comes to a halt. Which tier data center was designed and constructed by Katie's team?