You are just hired as the new CISO and are being briefed on all the Information Security projects that your section has on going. You discover that most projects are behind schedule and over budget.

Using the best business practices for project management you determine that the project correct aligns with the company goals. What needs to be verified FIRST?

A.
Scope of the project
Answers
A.
Scope of the project
B.
Training of the personnel on the project
Answers
B.
Training of the personnel on the project
C.
Timeline of the project milestones
Answers
C.
Timeline of the project milestones
D.
Vendor for the project
Answers
D.
Vendor for the project
Suggested answer: A