You are just hired as the new CISO and are being briefed on all the Information Security projects that your section has on going. You discover that most projects are behind schedule and over budget.

Using the best business practices for project management you determine that the project correctly aligns with the company goals and the scope of the project is correct. What is the NEXT step?

A.
Review time schedules
Answers
A.
Review time schedules
B.
Verify budget
Answers
B.
Verify budget
C.
Verify resources
Answers
C.
Verify resources
D.
Verify constraints
Answers
D.
Verify constraints
Suggested answer: C