The new CISO was informed of all the Information Security projects that the organization has in progress. Two projects are over a year behind schedule and over budget. Using best business practices for project management you determine that the project correctly aligns with the company goals.

Which of the following needs to be performed NEXT?

A.
Verify the scope of the project
Answers
A.
Verify the scope of the project
B.
Verify the regulatory requirements
Answers
B.
Verify the regulatory requirements
C.
Verify technical resources
Answers
C.
Verify technical resources
D.
Verify capacity constraints
Answers
D.
Verify capacity constraints
Suggested answer: A