Refer to the exhibit.

An OT architect has implemented a Modbus TCP with a simulation server Conpot to identify and control the Modus traffic in the OT network. The FortiGate-Edge device is configured with a software switch interface ssw-01.

Based on the topology shown in the exhibit, which two statements about the successful simulation of traffic between client and server are true? (Choose two.)

A.
The FortiGate-Edge device must be in NAT mode.
Answers
A.
The FortiGate-Edge device must be in NAT mode.
B.
NAT is disabled in the FortiGate firewall policy from port3 to ssw-01.
Answers
B.
NAT is disabled in the FortiGate firewall policy from port3 to ssw-01.
C.
The FortiGate devices is in offline IDS mode.
Answers
C.
The FortiGate devices is in offline IDS mode.
D.
Port5 is not a member of the software switch.
Answers
D.
Port5 is not a member of the software switch.
Suggested answer: A, B