What are two critical tasks the OT network auditors must perform during OT network risk assessment and management? (Choose two.)

A.
Planning a threat hunting strategy
Answers
A.
Planning a threat hunting strategy
B.
Implementing strategies to automatically bring PLCs offline
Answers
B.
Implementing strategies to automatically bring PLCs offline
C.
Creating disaster recovery plans to switch operations to a backup plant
Answers
C.
Creating disaster recovery plans to switch operations to a backup plant
D.
Evaluating what can go wrong before it happens
Answers
D.
Evaluating what can go wrong before it happens
Suggested answer: A, C