Question 692 - H12-224 discussion
Which of the following statements regarding the operation window time for a software upgrade is false?
A.
It is determined by the accepted service interruption duration.
B.
It must be longer than the upgrade execution time.
C.
Troubleshooting time must be reserved.
D.
Only network maintenance personnel need to be notified of the operation window time, while the customer does not.