List of questions
Related questions
Question 13 - H12-351_V1.0 discussion
In a VRRP HSB scenario, if the VRRP preemption delay is set to a small value, which of the following problems may occur after a master/backup switchover? (Select All that apply)
A.
The batch backup process cannot be started.
B.
A master/backup switchback is triggered too quickly.
C.
Backup information is incomplete.
D.
Service data on the master and backup WACs is lost.
Your answer:
0 comments