Which of the following is least likely to help ensure that risk is considered in a work program?

A.
Risks are discussed with audit client.
Answers
A.
Risks are discussed with audit client.
B.
All available information from the risk-based plan is used.
Answers
B.
All available information from the risk-based plan is used.
C.
Client efforts to affect risk management are considered.
Answers
C.
Client efforts to affect risk management are considered.
D.
Prior risk assessments are considered.
Answers
D.
Prior risk assessments are considered.
Suggested answer: A

Explanation:

While discussing risks with the audit client can provide useful insights, it is the least structured method compared to using all available information from the risk-based plan, considering client efforts to manage risk, and reviewing prior risk assessments. These latter methods are more systematic and ensure that the audit work program is comprehensive and focused on relevant risks.

Reference: = IIA Standard 2200 - Engagement Planning, IIA Practice Guide: ''Developing the Audit Plan''.