An internal auditor is conducting an assessment of the purchasing department. She has worked the full amount of hours budgeted for the engagement; however, the audit objectives are not yet complete. According to IIA guidance, which of the following are appropriate options available to the chief audit executive?

1. Allow the auditor to decide whether to extend the audit engagement.

2. Determine whether the work already completed is sufficient to conclude the engagement.

3. Provide the auditor feedback on areas of improvement for future engagements.

4. Provide the auditor with instructions and directions to complete the audit.

A.
1, 2, and 3
Answers
A.
1, 2, and 3
B.
1, 2, and 4
Answers
B.
1, 2, and 4
C.
1, 3, and 4
Answers
C.
1, 3, and 4
D.
2, 3, and 4
Answers
D.
2, 3, and 4
Suggested answer: D

Explanation:

According to IIA guidance, the chief audit executive (CAE) has several appropriate options when the audit objectives are not complete despite the auditor having worked the full amount of budgeted hours. The CAE should determine if the work already completed is sufficient to conclude the engagement (2). The CAE should also provide feedback on areas of improvement for future engagements (3) and give instructions and directions to complete the audit (4). Allowing the auditor to decide whether to extend the audit engagement (1) is not typically an appropriate option as this decision should involve senior management or the CAE to ensure alignment with organizational priorities and resource allocation.

Reference: = IIA Standard 2010 - Planning, IIA Standard 2020 - Communication and Approval, IIA Standard 2040 - Policies and Procedures.