You have identified a task in your task list that cannot be completed until the inspector for the project signs off on the initial deliverables.

The inspector's signoff on the initial deliverables is called what?

A.
Assumption
Answers
A.
Assumption
B.
Dependency
Answers
B.
Dependency
C.
Milestone
Answers
C.
Milestone
D.
Constraint
Answers
D.
Constraint
Suggested answer: B