Due to the complexity of a project, the project board is concerned that the business analyst (BA) will not be able to ensure all requirements are verified. What tool can the BA present to the project board to mitigate their concern?

A.
Data model
Answers
A.
Data model
B.
Use case diagram
Answers
B.
Use case diagram
C.
Business analysis checklist
Answers
C.
Business analysis checklist
D.
Risk register
Answers
D.
Risk register
Suggested answer: A