Question 33 - CBAP discussion

Report
Export

When can changes to requirements occur in a business analysis planning and monitoring assignment?

A.
Change to requirements can occur any time before the project scope statement is created.
Answers
A.
Change to requirements can occur any time before the project scope statement is created.
B.
Changes to requirements can occur at any time.
Answers
B.
Changes to requirements can occur at any time.
C.
Changes to requirements can occur any time after the project's change control system has been enacted.
Answers
C.
Changes to requirements can occur any time after the project's change control system has been enacted.
D.
Change to requirements can occur at any time before the key stakeholders approve the identified requirements.
Answers
D.
Change to requirements can occur at any time before the key stakeholders approve the identified requirements.
Suggested answer: B
asked 18/09/2024
Padmavathi Jawaharlal
35 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first