Question 33 - CBAP discussion
When can changes to requirements occur in a business analysis planning and monitoring assignment?
A.
Change to requirements can occur any time before the project scope statement is created.
B.
Changes to requirements can occur at any time.
C.
Changes to requirements can occur any time after the project's change control system has been enacted.
D.
Change to requirements can occur at any time before the key stakeholders approve the identified requirements.