You are the business analyst for your organization and you are preparing the business case for a proposed solution. You need to include the management horizon in your business case.

What is the management horizon?

A.
It is the expected deliverables that will be beneficial for the organization.
Answers
A.
It is the expected deliverables that will be beneficial for the organization.
B.
It is the point in time when the solution will be completed.
Answers
B.
It is the point in time when the solution will be completed.
C.
It is the duration of each phase of the project until the solution earns a profit.
Answers
C.
It is the duration of each phase of the project until the solution earns a profit.
D.
It is the point in time for the solution to break even on cost and begin earning a profit.
Answers
D.
It is the point in time for the solution to break even on cost and begin earning a profit.
Suggested answer: D