Your organization is trying to determine which one of two opportunities they will pursue. The Project A is worth $235,987 and Project B is worth $567,000 but carries significant risk. The organization elects to purse Project B and not Project A.

What is the opportunity cost in this scenario?

A.
$331013
Answers
A.
$331013
B.
There is not enough information to know as the risk for Project B has not been quantified.
Answers
B.
There is not enough information to know as the risk for Project B has not been quantified.
C.
$235,987
Answers
C.
$235,987
D.
$567,000
Answers
D.
$567,000
Suggested answer: C