You are the business analyst for your organization. You are coaching Tom about the different approaches to business analysis.

Which type of business analysis approach has the most business analysis work at the beginning of the project or during the start of a project phase?

A.
Change-driven approach
Answers
A.
Change-driven approach
B.
Value-driven approach
Answers
B.
Value-driven approach
C.
Plan-driven approach
Answers
C.
Plan-driven approach
D.
Requirements-driven approach
Answers
D.
Requirements-driven approach
Suggested answer: C