Which of the following is an estimate based on past projects to predict the current cost and/or duration of the current project?

A.
Current estimate
Answers
A.
Current estimate
B.
Past project cost
Answers
B.
Past project cost
C.
Past estimate
Answers
C.
Past estimate
D.
Top-down estimate
Answers
D.
Top-down estimate
Suggested answer: D