When is stakeholder analysis performed?

A.
As soon as the project charter is created.
Answers
A.
As soon as the project charter is created.
B.
As soon as the project sponsor is named.
Answers
B.
As soon as the project sponsor is named.
C.
As soon as a business need is identified.
Answers
C.
As soon as a business need is identified.
D.
As soon as a business solution is identified.
Answers
D.
As soon as a business solution is identified.
Suggested answer: C