Which of the following is a narrative description of the work required for the project?

A.
Contract work breakdown structure (CWBS)
Answers
A.
Contract work breakdown structure (CWBS)
B.
Work breakdown structure (WBS)
Answers
B.
Work breakdown structure (WBS)
C.
Contract statement of work (CSOW)
Answers
C.
Contract statement of work (CSOW)
D.
Statement of work (SOW)
Answers
D.
Statement of work (SOW)
Suggested answer: D