The RGQ Organization utilizes a change log.

What is a change log?

A.
It is a document that records all change requests for the project.
Answers
A.
It is a document that records all change requests for the project.
B.
It is a document that tracks all unauthorized changes to the project solution.
Answers
B.
It is a document that tracks all unauthorized changes to the project solution.
C.
It is a document that tracks all characteristics and status of changes that have been received.
Answers
C.
It is a document that tracks all characteristics and status of changes that have been received.
D.
It is a document that tracks the changes that have been received, including their implementation to the project solution.
Answers
D.
It is a document that tracks the changes that have been received, including their implementation to the project solution.
Suggested answer: C