Which of the following inputs of Monitor and Control Risks acquires information from performance measurements and evaluates it to provide variance analysis and forecasting?

A.
Risk register
Answers
A.
Risk register
B.
Work performance information
Answers
B.
Work performance information
C.
Performance report
Answers
C.
Performance report
D.
Project management plan
Answers
D.
Project management plan
Suggested answer: C