Which of the following is a process of adding labor to a project to reduce the project duration?

A.
Forming
Answers
A.
Forming
B.
Storming
Answers
B.
Storming
C.
Rolling wave planning
Answers
C.
Rolling wave planning
D.
Crashing
Answers
D.
Crashing
Suggested answer: D