Which of the following reports is generated whenever the project is slipping off the project schedule and includes an explanation of the problem?

A.
Status report
Answers
A.
Status report
B.
Schedule variance report
Answers
B.
Schedule variance report
C.
Delay report
Answers
C.
Delay report
D.
Answers
D.
Suggested answer: B

Explanation:

A. Status report

B. Schedule variance report

C. Delay report

D. Cost variance report

Answer: B