Which of the following graphical presentations of a project plan is most appropriate for presenting to upper management?

A.
Pie chart
Answers
A.
Pie chart
B.
Pareto Chat
Answers
B.
Pareto Chat
C.
Critical Path Method
Answers
C.
Critical Path Method
D.
Scatter chart
Answers
D.
Scatter chart
Suggested answer: C