Which of the following defines the deliverable the customer is expecting?

A.
Project charter
Answers
A.
Project charter
B.
Procurement management plan
Answers
B.
Procurement management plan
C.
Product scope statement
Answers
C.
Product scope statement
D.
Project network diagram
Answers
D.
Project network diagram
Suggested answer: C