Question 318 - CBAP discussion
An online stock trading system is under implementation.
Which of the following events can be considered as a trigger for re-prioritization?
A.
A team member has left the project and is being replaced
B.
A new initial public offering in the stock market is introduced
C.
Further dependencies among solution components are uncovered
D.
Number of reported quality defects is growing through phases