A business analyst (BA) has been coordinating several meetings with stakeholders to reach consensus regarding the solution design to implement a global currency exchange system for an international bank. Consensus has not been reached yet, although BA has great communication skills and is trusted by all stakeholders. The stakeholders formally approved the business need initially.
Why is there disagreement?
A.
The requirements are interpreted differently by each stakeholder.
B.
The requirements are incorrectly traced.
C.
The approval authority for the solution is unclear.
D.
More solution alternatives need to be generated.