Question 344 - CBAP discussion
A project is implemented using a predictive approach. Unfortunately, a lot of change requests (CR) have been raised. A project manager (PM), who should approve each change request, is overworked.
What could the business analyst (BA) propose to make things better?
A.
Approve the CRs independently for the PM
B.
Transfer responsibility from the PM to a project's sponsor
C.
Revisit the Business Analysis Governance approach
D.
Decline CRs because of the approach
Your answer: