During the testing phase, a new requirement surfaced and the stakeholder asked the developer to modify the code without informing the business analyst (BA).
The BA became aware of the new functionality after a defect was raised against another component of the design. The BA can keep this situation from occurring in the future by creating a:
A.
stakeholder engagement plan
B.
change control process
C.
risk strategy
D.
prioritization approach