A business analyst (BA) on a project is in the process of validating requirements and finds that there is a high degree of uncertainty related to one of the assumptions being true. The BA adds the assumption to the risk register and performs a full risk analysis to handle this situation. What type of strategy is in place if the organization is risk-averse?
A.
Acceptance
B.
Avoidance
C.
Mitigation
D.
Transfer