The board of directors of an enterprise has approved a three-year IT strategic program to centralize the core business processes of its global entities into one core system. Which of the following should be the ClO's NEXT step?
A.
Engage a team to perform a business impact analysis (BIA).
B.
Require the development of a risk management plan.
C.
Determine resource requirements for program implementation.
D.
Require the development of a program roadmap.