List of questions
Related questions
Question 160 - CGEIT discussion
A rail transport company has the worst on-time arrival record in the industry due to an antiquated IT system that controls scheduling. Despite employee resistance, an initiative lo upgrade the technology and related processes has been approved. To maximize employee engagement throughout the project, which of the following should be in place prior to the start of the initiative?
A.
Procurement management plan
B.
Organizational change management plan
C.
Risk response plan
D.
Resource management plan
Your answer:
0 comments
Sorted by
Leave a comment first