Question 167 - CGEIT discussion
An executive sponsor of a partially completed IT project has learned that the financial assumptions supporting the project have changed. Which of the following governance actions should be taken FIRST?
A.
Schedule an interim project review.
B.
Request a risk assessment.
C.
Re-evaluate the project in the portfolio.
D.
Request an update to the business case