Question 177 - CGEIT discussion
Which of the following would be of MOST concern regarding the effectiveness of risk management processes?
A.
Key risk indicators (KRIs) are not established.
B.
Risk management requirements are not included in performance reviews.
C.
The plans and procedures are not updated on an annual basis.
D.
There is no framework to ensure effective reporting of risk events.