An enterprise has identified a number of plausible risk scenarios that could result in economic loss associated with major IT investments. Which of the following is the BEST method to assess the risk?

A.
Cost-benefit analysis
Answers
A.
Cost-benefit analysis
B.
Qualitative analysis
Answers
B.
Qualitative analysis
C.
Business impact analysis (BIA)
Answers
C.
Business impact analysis (BIA)
D.
Quantitative analysis
Answers
D.
Quantitative analysis
Suggested answer: C