An enterprise is approaching the escalation date of a major IT risk. The IT steering committee wants to ascertain who is responsible for the risk response. Where should the committee find this information?

A.
Resource management plan
Answers
A.
Resource management plan
B.
RACl chart
Answers
B.
RACl chart
C.
Risk management plan
Answers
C.
Risk management plan
D.
Risk register
Answers
D.
Risk register
Suggested answer: D