Question 452 - CGEIT discussion
An IT strategy committee wants to ensure stakeholders understand who owns each strategic objective. To enable this understanding, which of the following should be communicated to stakeholders?
A.
A RACI chart
B.
The strategic plan
C.
Performance measure
D.
Risk owners