Question 266 - CISA discussion
Which of the following would BEST manage the risk of changes in requirements after the analysis phase of a business application development project?
A.
Expected deliverables meeting project deadlines
B.
Sign-off from the IT team
C.
Ongoing participation by relevant stakeholders
D.
Quality assurance (OA) review
Your answer: