Which of the following BEST facilitates strategic program management?

A.
Implementing stage gates
Answers
A.
Implementing stage gates
B.
Establishing a quality assurance (QA) process
Answers
B.
Establishing a quality assurance (QA) process
C.
Aligning projects with business portfolios
Answers
C.
Aligning projects with business portfolios
D.
Tracking key project milestones
Answers
D.
Tracking key project milestones
Suggested answer: C

Explanation:

The best option that facilitates strategic program management is aligning projects with business portfolios (option C). This is because:

Strategic program management is the coordinated planning, management, and execution of multiple related projects that are directed toward the same strategic goals12.

Aligning projects with business portfolios means ensuring that the projects within a program are aligned with the organization's strategic objectives, vision, and mission .

Aligning projects with business portfolios helps to prioritize the most valuable and impactful projects, optimize the allocation of resources, monitor the progress and performance of the program, and deliver the expected benefits and outcomes .

Implementing stage gates (option A) is a process of reviewing and approving projects at predefined points in their lifecycle to ensure that they meet the quality, scope, time, and cost criteria. While this can help to control and improve the project management process, it does not necessarily facilitate strategic program management, as it does not address the alignment of projects with business portfolios.

Establishing a quality assurance (QA) process (option B) is a process of ensuring that the project deliverables meet the quality standards and requirements of the stakeholders. While this can help to enhance the quality and satisfaction of the project outcomes, it does not necessarily facilitate strategic program management, as it does not address the alignment of projects with business portfolios.

Tracking key project milestones (option D) is a process of monitoring and reporting the completion of significant events or deliverables in a project. While this can help to measure and communicate the progress and status of the project, it does not necessarily facilitate strategic program management, as it does not address the alignment of projects with business portfolios.

Therefore, the best option that facilitates strategic program management is aligning projects with business portfolios (option C), as this ensures that the projects within a program are consistent with the organization's strategic goals and objectives.