Question 1053 - CISA discussion
Which of the following is the MAIN risk associated with adding a new system functionality during the development phase without following a project change management process?
A.
The added functionality has not been documented.
B.
The new functionality may not meet requirements.
C.
The project may fail to meet the established deadline.
D.
The project may go over budget.