When assessing the maturity level of an organization's risk management framework, which of the following deficiencies should be of GREATEST concern to a risk practitioner?

A.
Unclear organizational risk appetite
Answers
A.
Unclear organizational risk appetite
B.
Lack of senior management participation
Answers
B.
Lack of senior management participation
C.
Use of highly customized control frameworks
Answers
C.
Use of highly customized control frameworks
D.
Reliance on qualitative analysis methods
Answers
D.
Reliance on qualitative analysis methods
Suggested answer: C