Which of the following is MOST helpful in verifying that the implementation of a risk mitigation control has been completed as intended?

A.
An updated risk register
Answers
A.
An updated risk register
B.
Risk assessment results
Answers
B.
Risk assessment results
C.
Technical control validation
Answers
C.
Technical control validation
D.
Control testing results
Answers
D.
Control testing results
Suggested answer: D