An organization's recovery team is attempting to recover critical data backups following a major flood in its data center. However, key team members do not know exactly what steps should be taken to address this crisis. Which of the following is the MOST likely cause of this situation?
A.
Failure to test the disaster recovery plan (DRP)
B.
Lack of well-documented business impact analysis (BIA)
C.
Lack of annual updates to the disaster recovery plan (DRP)
D.
Significant changes in management personnel