Question 1040 - CRISC discussion
A control process has been implemented in response to a new regulatory requirement, but has significantly reduced productivity. Which of the following is the BEST way to resolve this concern?
A.
Absorb the loss in productivity.
B.
Request a waiver to the requirements.
C.
Escalate the issue to senior management
D.
Remove the control to accommodate business objectives.